Jet Grout Barrier Wall Completed!
Focus Shifts to Operable Unit 2
Operable Unit 1 (40 Willow Avenue)
National Grid and NYSDEC Reached a Major Milestone on the Final Major Phase of Remediation of OU-1 (40 Willow Ave. Sector) of Former Manufactured Gas Plant (MGP) Site.
The New York State Department of Environmental Conservation (NYSDEC) and National Grid (formerly KeySpan) have completed the installation of the jet grout barrier wall at the sector of the former manufactured gas plant site on which the gas holder and supporting facilities were located (the OU-1, 40 Willow Avenue parcel). Quality assurance coring and hydrogeologic testing of select areas of the barrier wall have been completed, and the four walls have been certified by the Engineer-of-Record. All site restoration activities have been completed and the jet grout and waste management contractors have demobilized from the site.
Field activities to monitor and study the potential for removing Dense Non-Aqueous Phase Liquid (DNAPL) from within the containment barrier were initiated in December 2009. Pilot wells were placed within the holder foundation, adjacent to the former holder to evaluate soils just below the bottom of the holder foundation, and within coarse grained soils located at significant depths outside of the holder. The next step is to perform a short-term recoverability test and analyze the results. The following bullet points detail ongoing and future anticipated activities on the OU-1 site.
Ongoing activities:
- Began well development of three NAPL recovery wells within the jet grout barrier wall in support of the NYSDEC approved NAPL recovery pilot test.
- Continued monthly groundwater sampling within the Lynhurst Avenue #53 buffer zone as required by NYSDEC/DOH.
Future (two week look-ahead) activities:
- Complete development of NAPL recovery pilot test wells at the concrete work platform within the jet grout barrier wall.
- Finalize the Clifton OU-1 Construction Completion Report and submit to NYSDEC/DOH.
Recently Completed Activities:
- Installed three DNAPL recovery wells within the jet grout barrier containment walls.
- Performed CAMP monitoring during the drilling and waste management activities.
Operable Unit 2 (25 Willow Avenue)
With the completion of the OU-1 barrier wall installation, focus now shifts to the remedial design investigation and remedial construction of OU-2. OU-2 is the site of the former manufactured gas plant that previously operated at 25 Willow Avenue and was closed in 1957. There are two off-site areas that are located adjacent to OU-2 at 89 Willow Avenue and 1 Edgewater Street. The remedial activities at OU-2 have progressed with the approval of the final remedial design work plan by NYSDEC and NYSDOH, including activities to be conducted during Preliminary Design Investigation (PDI). PDI activities were initiated in December and consist of utility preclearance, geophysical surveys, test pit excavations, and drilling activities (soil pre-characterization for final disposal and geotechnical) throughout the OU-2 properties. The PDI activities are conducted to provide additional design related data.
Ongoing activities:
- Initiated pre-characterization and geotechnical drilling on the OU-2 properties.
Future (two week look-ahead) activities:
- Continue drilling activities on the OU-2 properties.
- Initiate test pit excavation.
Completed Activities:
- Completed utility preclearance and the geophysical survey for OU-2 properties.
Community Air Monitoring Plan Summary
Operable Unit 1 (40 Willow Avenue)
A Community Air Monitoring Plan (CAMP) is implemented when intrusive activities are performed at Operable Unit 1. However, there were no intrusive activities at OU-1 during the month of January that required CAMP monitoring. Copies of previous weekly CAMP reports and other site documents for OU-1 are stored at the two public document repositories for the project.
Operable Unit 2 (25 Willow Avenue)
A Community Air Monitoring Plan (CAMP) is implemented in support of the PDI activities at the OU-2 properties during intrusive work . The CAMP consists of portable monitors placed upwind and downwind of the work area. Concentrations of vapors and dust associated with the pre-design investigation drilling and waste handling were below levels requiring action in the NYSDEC and NYSDOH approved plan.
The repositories are located at:
Community Board 1 One Edgewater Plaza Room 311 Staten Island, NY 10305 Phone #: (718) 981-6900 |
Borough President’s Office Borough Hall Staten Island, New York 10301 Phone #: (718) 816-2057 |
If you have any questions or comments about the work on the site, please use the site's Telephone Hotline at 718-982-7349.