Activity Updates

National Grid provides activity updates for neighbors of the Clifton former MGP site as developments related to site remediation occur. The updates will describe the work that is on-going at Operable Unit 2 (OU-2), located at 25 Willow Avenue, to remediate the former main operating portion of the Site that was closed in 1957. Two off-site areas with MGP residuals are located adjacent to the OU-2 Site at 89 Willow Avenue and between Edgewater Street and Bay Street at 1 Edgewater Street.

Remedial activity for Operable Unit 1 (40 Willow Avenue) has been completed and the parcel is now in the Operations, Maintenance & Monitoring (OM&M) phase. There will be no further updates for OU 1, but monitoring and other reports will be placed in the Key Documents/Major Reports section of this website as they are completed and approved. The Report Archive section under the Key Documents tab of this website will include all of the Updates.

Update Week Ending June 29, 2012

Remedial Contractor Continues Site Remediation

Barrier and Buttress Cement Bentonite Walls along Bay Street and Willow Avenue Are Now Complete

photo
Site showing temporary fabric structure over excavation area

On-going activities:

  • Continued the preparation and load-out of excavated cement bentonite wall (CBW) spoils from the temporary fabric structure (TFS) and transported the material in lined, covered trucks for proper disposal.
  • Initiated demobilization of the CBW contractor and equipment from the Site.
  • Continued sorting and load-out of debris from the one-story warehouse building for recycling and disposal.
  • Continued installation of dewatering well sleeves.
  • Continued installation of the storm water bypass system along Willow Avenue.
  • Continued the use of an odor suppressant misting system on the perimeter fence, TFS doors, applied odor suppressant liquid, foam, and plastic sheeting to prevent odors from leaving the Site.
  • Applied water throughout the Site to prevent the formation of dust.
  • Continued maintenance of erosion and sediment controls throughout the Site.
  • Continued general housekeeping activities at the Site.
  • Continued monitoring for noise, vibration, and settlement on Site and on neighboring properties.

photo
Site showing area where one story building was demolished

Recently completed activities:

  • Completed the excavation and installation of the barrier and buttress CBW along Willow Avenue.

Future near-term activities:

  • Complete sorting and load-out of debris from the demolition of the one-story warehouse building for recycling and disposal.
  • Initiate the installation of well points for dewatering areas of the Site to be excavated.
  • Complete excavating shallow excavation areas and backfilling.
  • Initiate systematic excavation throughout the Site beneath the TFS.

Community Air Monitoring Plan Summary

Community air monitoring, initiated in February 2012, continues as intrusive activities are conducted by the remediation contractor at OU-2. There were no exceedances of action levels during this period.

Staten Island Community Board #1
One Edgewater Plaza
Room 217
Staten Island, NY 10305
Phone #: (718) 981-6900
Borough President’s Office
Borough Hall
Staten Island, New York 10301
Phone #: (718) 816-2057

If you have any questions or comments about the work on the site, please use the Site Telephone Hotline at 718-982-7349.